AIA A201-2017 General Conditions (Arts. 3, 7, 9, 12, 14, 15) · NASCLA Contractor's Guide to Business, Law and Project Management (13th ed.) · OSHA 29 CFR 1926 (Subparts C and M) and 29 CFR 1910.1200 · OSHA 29 CFR 1904 (recording and reporting) · OSHA 3824, Resource for Development and Delivery of Training to Workers · NICET Code of Ethics · NFPA 72-2022 §10.5 and Ch. 7 · IBC-2021 Ch. 1 (Scope and Administration) · Outline tasks 3.4.1, 3.4.2

What NICET expects at Level III

Task 3.4 covers the work that is neither wiring nor programming: running the job (3.4.1) and leading people (3.4.2). A Level III technician supervises Level I and II technicians, deals with owners, general contractors, engineers, and AHJs, and answers for schedule, cost, quality, safety, and ethics. The study references for this area (the NASCLA Contractor's Guide, 13th ed.; OSHA 3824; the NICET Code of Ethics; and, for contract language, AIA A201-2017 and the OSHA rules) are not allowed in the test center, so these items reward vocabulary, a handful of numbers, and judgment that you already carry with you. Expect "what should the lead do first?" scenarios plus short story problems (markup and margin, retainage, float, earned value).

3.4.1 Supervise work activities

Scheduling

Cost control

ItemFormula or rule
Price from markupPrice = cost × (1 + markup)
Price from marginPrice = cost ÷ (1 − margin); a 25% markup equals a 20% margin
RetainageThe withheld percentage applies to cumulative work: net due = work to date × (1 − retainage) − previous payments
Overhead, then profitOverhead is a markup on cost, profit a margin on price: price = cost × (1 + overhead) ÷ (1 − profit margin)
Earned valueCPI = EV ÷ AC; SPI = EV ÷ PV; CV = EV − AC; SV = EV − PV; EAC = BAC ÷ CPI if current cost performance continues
Contract typesLump sum: the contractor carries cost risk. Cost-plus and time-and-material: the owner carries it unless a not-to-exceed amount caps it. Unit price: pay by measured quantity
Trap: markup is based on cost and margin is based on price. They are never the same number, and a bid priced with the wrong one loses money.

Contract documents and AIA A201-2017

TopicA201-2017Remember
Change Order§7.2Written; records agreement on the change, the Contract Sum, and the Contract Time
Construction Change Directive§7.3Directs a change before price and time are agreed; the Contractor proceeds promptly and states its position on the adjustment; if it disagrees, the Architect determines the adjustment (Claims: Art. 15)
Minor change§7.4No change in sum or time
Concealed conditions§3.7.4Notice before disturbing the condition and within 14 days (21 days in the 2007 edition)
Claims§15.1.3.1Written notice within 21 days of the event or of recognizing the condition, whichever is later
Cost claims§15.1.5Notice before proceeding with the Work (emergencies excepted)
Submittals§3.12.6, §3.12.8No Work that requires a submittal until it is approved (§3.12.6); approval does not excuse deviations that were not called out (§3.12.8)
Stored materials§9.3.2On-site storage is payable; off-site storage needs the Owner's advance approval, a written location, and title and insurance procedures
Stop work for nonpayment§9.7Seven additional days' written notice to Owner and Architect
Substantial Completion§9.8Owner can occupy or use the Work as intended; punch list at §9.8.2
Correction period§12.2.2.1, §12.2.5One year from Substantial Completion to correct nonconforming Work; special warranties are separate; the period does not limit the Contractor's other obligations (§12.2.5)
TerminationArt. 14Contractor: Work stopped 30 consecutive days through no fault of its own (§14.1.1), then seven days' written notice (§14.1.3). Owner for cause: seven days' notice (§14.2)

An RFI is a written question answered in writing and kept in a log. It does not change price or time by itself: if the answer adds scope, ask for a change order or directive before you build it.

Business and legal topics (NASCLA style)

Quality, risk, and communication

Jobsite safety supervision

TopicRule
Competent person1926.32(f): identifies hazards and has authority to correct them; 1926.20(b)(2): regular inspections by competent persons
Fall protection6 ft trigger on construction (1926.501(b)(1)); training record with name, date, trainer or employer signature (1926.503(b))
Hazard communication1910.1200: written program, accessible SDS, labels, training at initial assignment and when a new hazard is introduced
Recording300 Log, 300A Summary, 301 Report; enter within 7 calendar days (1904.29); post the 300A Feb. 1 to Apr. 30 (1904.32); keep 5 years (1904.33)
ReportingDeath within 8 h of learning of it; in-patient hospitalization, amputation, or loss of an eye within 24 h (1904.39), even for small employers
Multi-employer sitesCPL 02-00-124: creating, exposing, correcting, and controlling employers
Prime and subcontractor1926.16: a subcontractor assumes responsibility for its part of the work and the prime contractor keeps overall responsibility; a contract clause cannot remove either
Lockout/tagoutConstruction: 1926.417. Electrical work in existing facilities: 1910.333(b)(2) (Subpart S); 1910.147 excludes electrical utilization installations

3.4.2 Supervise team members

NICET Code of Ethics

Certificants have due regard for public safety, health, and well-being (and, if overruled where safety is endangered, notify the employer, the client, and other appropriate authorities); take only assignments they are competent to perform; work efficiently, competently, and honestly; admit their errors and never distort facts; avoid conflicts of interest, or disclose them in writing when unavoidable; avoid bribery; keep their proficiency current; not misrepresent qualifications; and keep client information confidential unless consent is given or the law requires disclosure.

Recertification: NICET certification runs three years and is renewed by documenting 90 continuing professional development (CPD) points in that period (NICET Policy 30).

Finding it in your printed books

What to tab in your books

SectionWhy
OSHA 29 CFR 1926.32(f)Competent person: identifies hazards AND has authority to correct them (study reference)
OSHA 1926.20(b)(2) / 1926.21(b)(2)Regular inspections by competent persons; employer instructs workers in recognizing unsafe conditions
OSHA 1926.501(b)(1) / 1926.503(b)Fall protection at 6 ft; training certification record (name, date, trainer or employer signature)
OSHA 29 CFR 1910.1200 (via 1926.59)Hazard communication: SDS accessible, labels, training at initial assignment and for new hazards
OSHA 29 CFR 1904.7 / .29(b)(3) / .32 / .33Recordable criteria; enter cases within 7 calendar days; 300A posted Feb. 1 to Apr. 30; records kept 5 years
OSHA 29 CFR 1904.39Report death within 8 h; hospitalization, amputation, loss of an eye within 24 h
OSHA CPL 02-00-124 / 29 CFR 1926.16Multi-employer citation policy; a subcontractor assumes responsibility for its part of the work
OSHA 29 CFR 1910.333(b)(2) / 1926.417Lockout/tagout of electrical equipment: Subpart S in existing facilities, 1926.417 in construction
AIA A201-2017 §7.2 to §7.4Change Order, Construction Change Directive, minor change
AIA A201-2017 §3.7.4 / §15.1.3.1Concealed conditions 14 days; claims 21 days
AIA A201-2017 §9.7 / Art. 14Stop work after 7 additional days' notice; termination rights (30 consecutive days; 7 days)
AIA A201-2017 §9.3.2 / §9.8Stored materials need Owner approval and title protection; Substantial Completion
AIA A201-2017 §12.2.2.1 / §12.2.5One-year correction period; it is not a limit on the Contractor's other obligations
NASCLA Guide (13th ed.)Scheduling, estimating, contract types, bonds, liens, insurance (study reference)
OSHA 3824ADDIE, needs assessment, two-thirds activity-based, class of about 25, three evaluation types (study reference)
NICET Code of EthicsPublic safety, competence, honesty, conflicts of interest, confidentiality (nicet.org)
NICET Policy 30Recertification: 90 CPD points in a three-year period
NFPA 72-2022 §10.5.2Installation personnel qualified or supervised by qualified persons
NFPA 72-2022 §7.5.6 / §7.7Record of completion; records and their storage
IBC-2021 §107.4 / §110 / §111 / §115Amended documents resubmitted; inspections; certificate of occupancy; stop work order

Chapter vocabulary

Critical path
Longest chain of dependent activities; it sets the shortest possible project duration and has zero total float.
Total float
Time an activity can slip without delaying the project finish (LS − ES).
Free float
Time an activity can slip without delaying the early start of any successor.
Lead time
Time from placing an order to delivery of the item; in scheduling software it can also mean an overlap between linked activities.
Resource leveling
Shifting work, usually within float, so that resource demand does not exceed availability; it can extend the finish date.
Crashing
Adding resources to critical-path activities to shorten the schedule, at added cost; take the lowest cost per day first and re-check the network.
Fast tracking
Overlapping activities that were planned in sequence to shorten the schedule; it raises rework risk.
Markup
Percentage added to cost to obtain the price: price = cost × (1 + markup).
Gross margin
Profit as a percentage of the selling price: price = cost ÷ (1 − margin).
Retainage
Percentage of each progress payment withheld until completion to secure performance.
Change Order
Written instrument signed by Owner, Contractor, and Architect recording agreement on a change in the Work and any adjustment in Contract Sum and Time (A201-2017 §7.2).
Construction Change Directive (CCD)
Written order that directs a change in the Work before the adjustment in price or time is agreed (A201-2017 §7.3).
Request for Information (RFI)
Written request from the contractor to clarify the contract documents, answered in writing and logged.
Substantial Completion
Stage at which the Work is sufficiently complete in accordance with the Contract Documents that the Owner can occupy or use it for its intended purpose (A201-2017 §9.8.1).
Claim
Demand by Owner or Contractor for an adjustment of terms, payment of money, or extension of time; notice within 21 days (A201-2017 §15.1.3.1).
Bid bond
Surety guarantee that the bidder will sign the contract and furnish required bonds if awarded.
Performance and payment bonds
Surety guarantees that the contractor will complete the contract and that subcontractors and suppliers will be paid.
Mechanic's lien
Statutory claim against real property by those who furnished unpaid labor or material; notices and deadlines vary by state.
Lien waiver
Document releasing lien rights; a conditional waiver takes effect only when payment is received.
Quality assurance / quality control
QA is the planned system that prevents defects; QC is the inspection and testing that detects them.
Competent person
OSHA: one who can identify existing and predictable hazards and who is authorized to take prompt corrective measures (1926.32(f)).
Recordable case
Work-related injury or illness meeting the OSHA 1904 criteria, such as medical treatment beyond first aid, days away, or restricted work.
Earned value (EV)
Budgeted value of the work actually performed; CPI = EV ÷ AC and SPI = EV ÷ PV.
ADDIE
Instructional design model: Analysis, Design, Development, Implementation, Evaluation.
Conflict of interest
Situation in which a personal interest could influence, or appear to influence, professional judgment; disclose it in writing when it cannot be avoided.