Technical Documents, Drawings, and Submittals (NFPA 72-2022 Ch. 7)

NFPA 72-2022 Ch. 7 · NFPA 72-2022 §14.6 · NFPA 72-2022 §10.3 · NEC 2020 Ch. 9, Table 8 · Ugly's Electrical References 2020 · CSI MasterFormat · Outline tasks 1.3.1, 1.2.1, 1.1.1

What NICET expects from a Level I technician

Task 1.3.1 Knowledge of technical documents belongs to domain 1.3 (Submittal Preparation and System Layout), which is worth 1 to 11 percent of the exam (roughly 1 to 9 of the 85 questions). Level I candidates are not asked to design: you are expected to recognize, read, and use the project documents (shop drawings, riser, wiring diagrams, data sheets, sequence of operation, completion and inspection records) and to know what Chapter 7 of NFPA 72-2022 requires. These documents also show up inside installation (1.1.1) and testing (1.2.1) questions: where the candela is shown, where the EOL goes, which form is filled out, and how long records are kept.

Map of Chapter 7 (NFPA 72-2022)

SectionTopicMost frequently asked
7.2.1Minimum documentation (when the AHJ requires it)17-item list: narrative, riser, floor plans, sequence, data sheets, calculations, candela, records, software, record drawings
7.3Design (layout) documents7.3.3.6 and 7.3.3.7: indicate pathway class (12.3) and survivability level (12.4)
7.4Shop drawings7.4.2 scale; 7.4.4 general information and NFPA 170 symbols; 7.4.5 floor plans; 7.4.6 riser; 7.4.7 control unit; 7.4.8 typical wiring; 7.4.9 sequence; 7.4.10 calculations
7.5Completion documentation7.5.3 delivery; 7.5.5 record drawings; 7.5.6 record of completion; 7.5.7 site-specific software; 7.5.8 verification
7.6ITM documentation7.6.1 test plan (14.2.10); 7.6.6 record of inspection and testing
7.7Records, retention, and access7.7.1 records; 7.7.2 SYSTEM RECORD DOCUMENTS cabinet; 7.7.3 security
7.8FormsFigures 7.8.2(a) through 7.8.2(m)

Minimum documentation (7.2.1): learn it in groups

Shop drawings (7.4): what to look for in each document

DocumentKey contentSection
All drawingsIndicated scale, uniform sheet size, a plan of each floor; name of the protected premises, owner, and occupant; installer; location; device legend and symbols per NFPA 170 (or others acceptable to the AHJ); date of issue and revision dates7.4.2, 7.4.4
Floor planFloor, north arrow, graphic scale, walls and doors, partitions extending to within the top 15 percent of the ceiling height, room use, devices, primary power disconnecting means, interfaces with other systems, risers, type and number of devices on each circuit, conductors and conduit, ceilings over 10 ft (3.0 m), beams, acoustics, pathway class (with EOL location) and survivability7.4.5
RiserGeneral arrangement in building cross-section, number of risers, circuits per riser, devices per circuit on each floor, number of conductors per circuit, pathway class and survivability7.4.6
Control unit diagramEquipment and location; field wiring terminals and their identification; circuits connected; indicators and controls; connections to supervising station, releasing, and emergency control functions7.4.7
Typical wiringInitiating devices, notification appliances, remote indicators, annunciators, remote test stations, EOL and power supervisory devices7.4.8
Sequence of operationNarrative or input/output matrix (see Figure A.14.6.1.1)7.4.9
CalculationsBatteries, NAC voltage drop, others (line resistance)7.4.10

Completion, software, and the documentation cabinet

Forms (7.8.2) and record retention

FigureForm
7.8.2(a)System Record of Completion
7.8.2(b)–(f)Completion supplements: ECS, power systems, NAC power extender panels, interconnected systems, code deviations
7.8.2(g)System Record of Inspection and Testing
7.8.2(h)–(l)ITM supplements: notification appliances, initiating devices, MNS, ECS, interface components
7.8.2(m)Single- and multiple-station alarms and household systems
RecordRetentionSection
Inspection, testing, and maintenanceUntil the next test + 1 year14.6.2.1
Permanent (record drawings, O&M manuals, sequence of operation)Life of the system, kept by the owner14.6.1.3
MediumMust last the whole retention period; paper or electronic14.6.2.3

Reading drawings

Formula: actual distance = measurement on the drawing (in.) × feet per inch.

Scale1 in. on the drawing =Example
1/8 in. = 1 ft-0 in.8 ft3-3/4 in. → 30 ft
3/16 in. = 1 ft-0 in.5.33 ft3 in. → 16 ft
1/4 in. = 1 ft-0 in.4 ft7-1/2 in. → 30 ft
1/2 in. = 1 ft-0 in.2 ft2-1/2 in. → 5 ft
1 in. = 20 ft (engineering)20 ft1-1/2 in. → 30 ft

Construction documents

Ugly's / NEC Ch. 9, Table 8 (uncoated copper)

AWGcmilΩ/kft solidΩ/kft stranded
1816207.777.95
1625804.894.99
1441103.073.14
1265301.931.98

R = (total conductor length ÷ 1000) × Ω/kft; in a 2-wire circuit the conductor length is twice the run length. VD = I × R.

Common traps:
Finding it fast in the printed code book: Chapter 7 is short, so one permanent tab at its first page plus tabs at 7.2.1 (minimum documentation list), 7.4 (shop drawings), 7.5.6 (record of completion), and the 7.8.2 forms will cover most questions. Every 7.x section is in Chapter 7; the 14.6 record-retention rules are at the end of Chapter 14. In the index at the back of NFPA 72, look up "Documentation", "Shop drawings", "Record drawings", "Record of completion", "Site-specific software", "Records", and "Forms". Highlight "SYSTEM RECORD DOCUMENTS", "1 year thereafter" (14.6.2.1), and "life of the system" (14.6.1.3). The typical input/output matrix is Figure A.14.6.1.1 in Annex A (an asterisk next to a section number means annex material exists). For NEC Chapter 9, Table 8 (Conductor Properties), tab the page near the back of the NEC or use the conductor table in Ugly's table of contents.

What to tab in your books

SectionWhy
NFPA 72 §7.2.1Minimum required documentation (17 items)
NFPA 72 §7.3.3Design documents: pathway class and survivability
NFPA 72 §7.4.2–7.4.4Scale, basis for record drawings, general information, and NFPA 170 symbols
NFPA 72 §7.4.5Floor plan drawing contents
NFPA 72 §7.4.6Riser diagram contents
NFPA 72 §7.4.7Control unit diagrams
NFPA 72 §7.4.8–7.4.10Typical wiring, sequence of operation, and calculations
NFPA 72 §7.5.3Documents delivered to the owner
NFPA 72 §7.5.5Record (as-built) drawings
NFPA 72 §7.5.6Record of completion: who completes it, revisions, electronic format
NFPA 72 §7.5.7Site-specific software and passwords
NFPA 72 §7.6.6Record of inspection and testing
NFPA 72 §7.7Records, SYSTEM RECORD DOCUMENTS cabinet, and security
NFPA 72 §7.8.2Forms, Figures 7.8.2(a) through 7.8.2(m)
NFPA 72 §14.6Permanent records and ITM record retention
NFPA 72 Figure A.14.6.1.1Typical input/output matrix
NFPA 72 §10.3.3Devices listed for use with the control unit (compatibility)
NEC 2020 Ch. 9, Table 8Conductor properties: cmil and resistance

Chapter vocabulary

Shop drawings
The contractor's installation drawings with device locations, riser, diagrams, and calculations; the basis for the record drawings (NFPA 72 §7.4).
Record (as-built) drawings
Shop drawings updated to reflect the actual installation of the system (§7.5.5).
Redlines
A working copy of the drawings on which field changes are marked in red; used to prepare the record drawings.
Riser diagram
A building cross-section showing circuits, devices per floor, and number of conductors (§7.4.6).
Reflected ceiling plan (RCP)
A ceiling plan drawn as if reflected onto the floor; shows lights, diffusers, ceiling heights, and beams.
Input/output matrix
A table showing which outputs each input produces; an accepted form of the sequence of operation (Figure A.14.6.1.1).
Sequence of operation
A description, in matrix or narrative form, of what the system does for each signal (§7.2.1(4), §7.4.9).
Written narrative
Text describing the intent and general operation of the system (§7.2.1(1)).
Record of completion
The form documenting the installed system; completed by the installing contractor (§7.5.6, Figure 7.8.2(a)).
Record of inspection and testing
The ITM form, Figure 7.8.2(g) through (l), or an alternative record with the same information (§7.6.6).
Site-specific software
The programming unique to the installation; a copy goes to the owner and an on-site copy is kept in nonrewritable memory (§7.5.7).
Documentation cabinet
A cabinet labeled SYSTEM RECORD DOCUMENTS where the record documentation is stored (§7.7.2).
Technical data sheet (cut sheet)
The manufacturer's document listing current draw, voltages, candela, listing, and compatibility of the equipment.
Manufacturer's published instructions
The installation, operation, and maintenance instructions that come with listed equipment.
Submittal
A package of data sheets, shop drawings, and calculations sent for review before installation.
Request for information (RFI)
A formal written question to the designer to clarify conflicts or omissions in the documents.
Change order
A document that authorizes a change in the contract's scope, cost, or schedule.
Punch list
A list of items to correct or finish before final acceptance.
Legend
The table on a drawing that defines each symbol and abbreviation (symbols per NFPA 170).
Graphic (bar) scale
A bar drawn on the sheet that stays valid even when the drawing is printed reduced.
Above finished floor (AFF)
The reference for mounting heights, measured from the finished floor.
Test plan
A written document that clearly establishes the scope of testing (§7.6.1, §14.2.10).
Pathway class designation
The circuit class (A, B, X, etc.) per 12.3; shown on the drawings with the EOL location.
Authority having jurisdiction (AHJ)
The organization or official that reviews plans, issues permits, and approves the installation.

40 practice questions cover this chapter, each with an explanation and the code section. Get lifetime access or try the free practice exam.